Project Status
Design packages: Finished 03/2021
Permit: finished 06/2021
Construction: Start date 12/2022 / Expected completion 06/2024
Scope of work
Architectural design, Structural/civil engineering design, mechanical engineering design, electrical engineering design,
interior design, permit preparation and construction supervision.
Description/Built up area
3 Story VILLA including 1 basement + 2 upper Floors / Total built up area 850m2